May-July 2011: The USGS is performing the RFI sampling at Parcel 6.
Steven Carpenter, Albuquerque District Ordnance and Explosives Safety Specialist, inspects one of three trench excavations at AOC 83 with a metal detector. None of the three trenches contained buried waste. |
May 3, 2011: Newly elected Zuni Governor Arlen Quetawki, Lt Governor Willard Zunie, Head Councilman Steve Boone, Councilman Loren Leekela, and FWDA POC Darrell Tsabetsaye meet with Army representatives at FWDA |

Governor Arlen Quetawki, Lt Governor Willard Zunie, Head Councilman Steve Boone, Councilman Loren Leekela tour igloo with Army representatives. |

Steven Smith, Mike Scoville, and Steven Carpenter describe the Hazardous Waste Management Unit in Parcel 3 to the Zuni Government Delegation. |
April 28, 2011: Newly appointed Navajo Nation representatives meet with Army representatives at FWDA |

Representatives from the Navajo Nation (Albert Damon, Tony Perry, and Franklin Jishie) discuss the Fort Wingate project with Steven Smith and Mike Chee. |

Representatives from the Navajo Nation (Albert Damon left, Franklin Jishie center, and Tony Perry right) along with Richard Cruz and Steven Smith tour an igloo. |
April 14, 2010: MG Dorko visit to FWDA and Albuquerque District’s Project Office at the Fort Wingate School. |

Maj. Gen. Dorko and Lt. Col. Colloton, the Albuquerque District Commander, arrive at FWDA. |

Maj. Gen. Dorko and Lt. Col. Colloton with the FWDA and Albuquerque Fort Wingate School Project Office teams. |
Workshop Area Building Demolition 2010. |

Contractor removing debris piles from Parcel 12.
|

Photo showing debris removal. |

Contractor personnel performing final inspection and cleanup of debris removal. |

Contractor removing Buildings 509 and 510, vacuum producer building and primary collector barricade. |

Wall demolition, Building 515, Ammunition painting/acid washout building. |

Building 520 Disassembly Work mount pier blast shield demolition. |

Building 522, Ammunition renovation building, showing interior blast wall demolition.
|

Building 528, Ammunition Maintenance Shop, Demolition of last internal blast walls.
|

Demolition of Building 528, Ammunition Maintenance Shop. Contractor excavating around foundation stem walls.
|

Building 528, Ammunition Maintenance Shop. Demolition and debris removal is complete. Contractor completing final site grading.
|

Building 535, Heating Plant, Inspector’s workshop. Trackhoe at rear removing foundation. Front Trackhoe segregating demolition debris for recycling.
|

Building 536, Inspector’s Workshop. Contractor removing interior blast wall. Trackhoe to right is segregating debris for recycling.
|

Building 536, Inspector’s Workshop. Loading dock ramp demolition.
|

Building 542, Ammunition Workshop. Contractor removing south end of building.
|
Building 524, Safety Shelter. Contractor removing timber framed, earth covered safety shelter.
|